Glossary

Changeover time

The time between the last good part of one series and the first good part of the next. It is pure downtime and therefore the starting point of every economic calculation in handling technology. Where a tool or roll change today ties up two people and an overhead crane, the changeover time saved is usually the bigger item than the physical strain saved.

Also
Setup time · Tool change time · Rüstzeit
Also known as
  • Setup time
  • Tool change time
  • Rüstzeit
01

From the last good part to the first good part

Changeover time starts with the last good part of the old job and ends with the first good part of the new one. It therefore covers more than swapping the tool: cooling down, disconnecting, removal, transport, installation, connecting, adjusting, start-up and the parts scrapped until release.

During this time the machine stands still. The cost results from the downtime multiplied by the machine hourly rate – and from what long changeovers force: large batches, high stock and little flexibility.

02

Separating internal and external setup

The method for reducing changeover time, known as SMED, begins with a distinction. Internal setup is everything that can only be done with the machine stopped. External setup can be done while the machine is still or already producing: staging the tool, preheating it, fetching aids, taking the old tool away.

The first step moves as much as possible to the outside. The second shortens what remains inside – with quick clamps, uniform connections and handling that does not wait.

03

Where handling costs time

With heavy tools, rolls and fixtures, transport is often the longest internal item.

  • Waiting for the overhead crane, which is needed elsewhere
  • Waiting for a second person or a crane operator
  • Slinging with chains and eye bolts that first have to be found
  • Repeated repositioning because the tool cannot enter the machine from above
  • Threading in by hand because the load cannot be guided finely on the crane
04

What a dedicated unit at the machine changes

A handling unit that belongs to the machine is available when the changeover happens. A load handling attachment matched to the tool does away with slinging. A guided movement allows one person to bring the tool in from the side and position it without swinging.

A calculation with assumed figures: if 15 minutes of waiting are eliminated per change and tools are changed three times a day on 220 days, that is 165 machine hours a year. The value this represents follows from the hourly rate of your own machine.

05

Safety during the change

Changeover is a special operating mode with its own hazards: heavy parts, hot surfaces, open guards, time pressure. A procedure that is faster because a safeguard is skipped is not a reduction. Good changeover concepts are faster because they remove travel and waiting.

What Entracon offers here is on the matching page.

See what we offer
Overview

Internal and external setup

Activity Type Approach
Fetch and stage the new tool External Do it before the stop
Preheat the tool External Preheating station next to the machine
Release and remove the old tool Internal Quick clamps, dedicated handling unit
Install and connect the new tool Internal Guided handling, quick couplings
Take the old tool to storage External Do it after restart
Frequently asked questions

Frequently asked questions about Changeover time

What counts towards changeover time?

The whole time from the last good part of the old job to the first good part of the new one – including adjustment, start-up and start-up scrap, not just the mechanical change.

What does SMED mean?

Single Minute Exchange of Die – a method for reducing changeover time that separates internal and external setup, moves activities to the outside and simplifies the remaining internal steps.

Is a dedicated handling unit worthwhile just for tool changes?

That depends on the number of changes and the hourly rate of the machine. Where people wait for the overhead crane today, the downtime saved is usually the largest item in the calculation.

Contact

Let's talk about your project.

One short conversation usually settles more than three quotations. Call or write — you will reach an engineer directly.

Reach Entracon

How can we help?

Chat is not staffed right now. We are back for you tomorrow from 08:00. Just request a call-back – we'll get back to you.
Send an e-mail info@entracon.de
Or call us directly +49 234 5414010