Rail system or jib crane: which support structure suits the workstation

A jib crane serves a circle, a rail system an area. That single distinction decides more about the economics of an installation than any choice of device below it – and it is regularly asked too late.

Author
Dr.-Ing. Philipp Schwittek
Reading time
8 minutes
Updated
06. September 2026
The key points
  • A jib serves a circle, a rail system any area you like.
  • The jib is cheaper but needs a foundation for the full tipping moment.
  • From two connected workstations the rail system is usually ahead.
  • The hall structure decides more often than the budget.
  • Anyone planning to extend later runs the rail through from the start.
01

Circle or area

The difference sounds academic and is not. A pillar jib reaches every point within its radius – but only within. If supply, processing and storage do not lie on the same circle, dead zones appear that are bridged either by hand or by a second device. A rail system, by contrast, maps a rectangle that adapts to the layout of the workstation instead of the other way round.

02

What the floor takes

The jib passes the whole tipping moment into its base. At 120 kg and 4 m outreach that is around 5 kNm plus dead weight – a foundation rarely already present in an existing hall. Usual industrial floors of 15 to 20 cm are not enough; a foundation block is needed, and that means core drilling, concrete and curing time. A rail system instead spreads its loads over several columns or hangs from the hall structure.

03

What the hall carries

Suspended rail systems are the most elegant solution: no column in the way, no floor work. But they assume the roof structure takes the additional load – and with halls from the seventies and eighties that is by no means a given. A check by a structural engineer costs little and belongs at the start, not the end. Where the hall does not carry, a floor-supported system bringing its own columns is the answer.

04

When the jib stays the right choice

It is not the inferior solution but the solution to a different case. A single workstation with a fixed layout, an operating position at a machine, a removal point at a press: there the circle is exactly the right geometry, the installation is erected in days, and the price is well below a rail installation. It also makes sense as a supplement to an existing rail where a single remote position has to be served.

05

The question to ask at the start

Not: which device do we need? But: what does this area look like in five years? A rail can be extended, a foundation cannot. Anyone serving two positions today who knows a third is coming runs the rail through and later only adds the trolley. That decision costs little at the start and saves a complete second installation later.

Overview

Support structures compared

Criterion Pillar jib Wall jib Rail system
Working area full circle half circle free area
Floor space column in the way none only if floor-supported
Structural requirement foundation block load-bearing wall roof or own columns
Extendable no no yes, by extension
Erection time days days one to two weeks
Worthwhile from one workstation one position at a wall two connected positions
Frequently asked questions

Frequently asked questions about Rail system or jib crane

From when does a rail system beat two jibs?

Usually from the second workstation, if the two are connected. Two jibs cost similarly to buy but need two foundations, occupy floor space twice and leave the zone between them unserved. We work it through case by case – the answer depends strongly on the floor.

Will our roof carry a suspended system?

That cannot be answered on the phone. The hall structural calculations or an inspection on site are needed; with halls up to the eighties, caution is appropriate. The check is the first step of planning, not the last – if it comes back negative it changes the whole design.

Can we extend an existing system later?

With a rail system yes, provided profile, capacity and suspension were sized for it. That is exactly why we ask about the plans for the area when specifying the first installation. A jib cannot be extended – there the reach is fixed with the foundation.

What about the overhead crane we have?

It can take the load but rarely the task: it serves the whole hall, swings on a rope and is slow in fine positioning. For recurring workstation tasks a dedicated device is almost always faster – and the crane stays free for the rest of the hall.

About the author

Dr.-Ing. Philipp Schwittek

Managing Director, Entracon Planungsgesellschaft mbH

Engineer with a doctorate, specialising in plant engineering, digital design and process automation – from simulation through to commissioning.

  • Sizing
  • Design
  • Plant engineering
  • Standards and safety
Contact

Still a question open?

A short conversation usually settles more than three quotations. You reach an engineer directly, not a queue.

Reach Entracon

How can we help?

Chat is not staffed right now. We are back for you tomorrow from 08:00. Just request a call-back – we'll get back to you.
Send an e-mail info@entracon.de
Or call us directly +49 234 5414010